Construction updates at Highland and Rio Grande: January/February 2021

Posted on Thu, 02/11/2021 - 12:54pm

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager RGC 1000 is quickly nearing completion. However, the college experienced a minor delay of a couple of weeks due to the impacts of a COVID-related shutdown that...

Continue reading


Inside Highland Phase 2: Music and MBPT

Posted on Thu, 12/17/2020 - 2:37pm

ACC Highland Campus' newest phase is nearing completion, and many departments have started the move-in process. The credit classes expected to start in spring 2021 -- and are therefore among the first to make the move -- are Culinary, Architectural...

Continue reading


Construction updates at Highland and Rio Grande: November 2020

Posted on Thu, 12/03/2020 - 9:09am

Rio Grande Campus RenovationsBy Paul Mason, Rio Grande Renovations Project Manager Over the last month, we've made a good bit of progress toward completing this project. We are only two months from substantial completion! Inside the building, on...

Continue reading


HLC2 Riverbat

Construction updates at Highland and Rio Grande: March/April 2020

Posted on Thu, 06/25/2020 - 10:29am

Despite a brief shutdown and some challenges with delayed deliveries due to the COVID-19 pandemic, construction marches forward on the Rio Grande and Highland campus projects, which both reached significant milestones in the past month. Rio Grande...

Continue reading