ACC Highland Campus Phase 2 progress continues despite the wet weather. The roofing on the north building is 95 percent complete and 65 percent complete on the south building, and exterior sheathing is 85 percent complete. In the paseo, exterior framing and sheathing is ongoing. The paseo stairs and roof connector bridge also have been poured. Waterproofing at all exterior openings is complete, minus the paseo area. Concrete walls at the performance hall are currently being installed. Interior framing; sheetrock installation; and mechanical, electrical, and plumbing work are all ongoing. Underground utility trenching is scheduled to begin soon.
Renovations are moving forward at Rio Grande Campus. The contractor is installing formwork in preparation for pouring an elevated concrete slab which will become a new floor level for the future Student Commons space. Walls have been poured at the north atrium and the south mechanical room. Additionally, air conditioning equipment has been delivered and set in the basement. Grading and electrical rough-in also has started in the ACCelerator. Steel framing is ongoing on levels one and two.
Add new comment